HVAC Assessment, Upgrade and Design in King Fahd International Airport – DACO
We are performing the role of technical and the design consultant to the client for the assessment of the complete HVAC system in KFIA and upgradation of the existing HVAC system with Energy Efficient systems. The central plant capacity is 25,000 TR. Our scope also included evaluation of the existing Chilled water system and performed Hydraulic analysis. The project covered the below building of the KFIA facility:-
- Central Plant
- Passenger Terminal building for all floors
- All Landside Buildings
- All Airside Buildings
- Administration Building
- Mosque Plaza & Connection Bridge
- Air Cargo building
- Parking Garage
- Concourse Boarding Building & Bridges
- Control Tower
- Main Fire Station